Severn Trent Water are working to deliver a new Wastewater Treatment Plant for the village of Loggerheads in Staffordshire.
Loggerheads STW
Project Overview
Once this project is complete, the Loggerheads site will have a capacity of approximately 3,700 PE (Population Equivalent) & the treated effluent quality will comply with the new phosphorous consent permit.
Our Scope included:
- STORTEC provided & installed 2-OFF Primary Settlement Tanks in our ULTRASTORE® Stainless Steel.
- Due to the hydraulics, these tanks are partially buried below ground.
- Part of the package was for STORTEC to design and construct the conical in-situ poured concrete bases, wall mounted lauders and half-bridge scraper mechanisms.
All elements from the design, manufacture and installation of this package were undertaken inhouse by STORTEC.
The complete package provided was not only a commercial and programme benefit to our client (Coffey) but also for Severn Trent Water.
Project Headlines
- Supply and Installation of 2-Off Primary Settlement Tanks.
- The site is a Wastewater Treatment Works.
- Innovative Package project.
- Collaborative Working.
Client
Severn Trent Water
End User
Severn Trent Water
Value
- £560,000.00
Scope
Supply & Installation of 2-OFF
Primary Settlement Tanks
Tank
- 2-OFF Primary Settlement Tanks
Diameter
- 8,539mm
Height
- 2,718mm
Volume
- 127m³