The original Tanks both been in service since 1981. With no drawing or historical records meant from outset a lot of the responsibility of the success of the project fell to experience and quickly adjust to what we discovered.
The tank was dismantled using our specialist lifting jacks. This meant that all work was carried out at ground level in a very controlled procedure led approach which enable the existing concrete base to be reused.
We incorporated multiple hold points within our RAMS to allow the assessments to be made by our Structural Engineer of the reusable elements and careful management by our QHSE Teams.